Its been 5 days since I have stopped by the velodrome and some great progress has taken place. The track is a little over 75% done and probably will be "finished" Wednesday or Thursday of this week. Here is a picture of a slightly different perspective. All I can say is man are those banks steep!
3 Comments
whohoo
Submitted by Anonymous (not verified) on
i am so excited to try out one of those fuji's they have on that track.
don't they need to do any sanding or finishing on the boards?
Points: 0
Finish
Submitted by David on
I will ask them tomorrow if i stop by. I will also take a picture of the type of "nail" they are using. I dont know how to describe it so i will take a picture.
Points: 0
Elevator Bolts
Submitted by Anonymous (not verified) on
Here is a picture of one:
http://www.maxilift.com/Accessories/bolts.asp
No sanding required, but maybe some putty over some of the bolts to ensure it's smooth. I rode the backstraight several days ago and it is remarkably smooth.