Please be advised that Niwot Road is currently unpaved between 55th Street and 63rd Street. Paving will start next week and we anticipates to have at least one layer of new pavement in place for the holiday weekend.

Even with the new pavement down, the road will remain under construction through the end of June. Cyclists should anticipate uneven pavement, ongoing construction activity, soft shoulders and significant delays as construction crews work to complete the project.

This work is the final phase of the 4.3 mile Neva/Niwot Shoulders project that when complete, will provide a new pavement surface along with 4-foot shoulders for the entire stretch of Neva and Niwot Road from US36 (Foothills Highway) to 95th Street in Niwot.

All schedules are subject to change due to weather or other factors. Please respond to this email if you’d like more information on this project. Updates are also available on the county website.

Please use caution when riding and remember, "Courtesy is Contagious"!!!!